Boronia Precinct LATM Plan

Share Boronia Precinct LATM Plan on Facebook Share Boronia Precinct LATM Plan on X (formerly Twitter) Share Boronia Precinct LATM Plan on Linkedin Email Boronia Precinct LATM Plan link

Update 22 June 2026

At its meeting on 4 May 2026, Council resolved that:

  1. Council adopt the revised Boronia Precinct LATM Concept Plan that has incorporated community and TfNSW feedback.
  2. Council note the project delivery timeline, with construction to commence in late 2026 and completion by mid-2027 (per the TfNSW Safer Roads Program grant agreement).

The LATM Plan has been updated in response to the submissions and incorporating TfNSW comments.

Next steps for the LATM project

Next steps in the process include:

  • Detailed Design: finalising the detailed design incorporating the feedback and taking into consideration site constraints (April to June 2026).
  • Procurement of construction contractor (July-Aug 2026).
  • Construction: commencing late 2026 and completed by 30 June 2027 to meet grant requirements.


Progress Update - 25 February 2026

At its meeting on 28 July 2025, Council resolved that:

1.1 The Boronia LATM Option C be adopted by Council.
1. 2. Detail designs be undertaken and community consultation be carried out prior to construction.

The community were able to view and have their say on the final concept design for the proposed traffic calming measures in this document. The concept design incorporates minor changes to better suit the Boronia Precinct road network environment and to address the feedback initially received by the community.

Works are expected to begin in late 2026.

A Community information session was held on Monday 9 March to give residents the chance to view the final concept design in person.

Background

Council has been successful in receiving State Government funding to create a 40km/h local area traffic zone in the Boronia precinct.

The Safer Roads Program grant from Transport for NSW will be used to implement a local area traffic management (LATM) plan that will improve traffic and road safety in the Boronia precinct.

Traffic calming devices will be installed in local streets inside the boundary of Pittwater, Ryde and Park Road and High Street as displayed below and within the Boronia Precinct Local Area Traffic Management Plan. The speed will be reduced to 40km/h on these streets.

The identified streets in the Boronia precinct are often used by motorists who are looking to avoid the main road network, but are not local road users (rat running). This causes extra stress on these identified local streets in Boronia, decreasing local amenity and increasing safety concerns.

The project aims to change driver behaviour by installing physical speed barriers such as speed humps and raised pedestrian crossings, and reinforcing that this is a local street precinct where lower safer speeds are appropriate.

Low speed zones lead to broader benefits in creating an environment that supports pedestrian activity and urban amenity.

At its Meeting on 24 February 2025, Council resolved to endorse the proposed traffic calming devices mentioned above within the Boronia Precinct Local Area Traffic Management Plan, and to place the proposal on public exhibition for a period of 28 days.

Community feedback was undertaken from Thursday 3 April to 5pm Sunday 4 May 2025.

A community meeting was also held at the Boronia Park Sports and Community Facility on Tuesday 29 April 2025.

All feedback will be collated and will be used to inform the detailed design.

Council is committed to ensuring the community has their say on any proposed changes to traffic conditions on local streets.

The projected must be completed by mid-2027 as per the grant agreement with Transport for NSW.

Update 22 June 2026

At its meeting on 4 May 2026, Council resolved that:

  1. Council adopt the revised Boronia Precinct LATM Concept Plan that has incorporated community and TfNSW feedback.
  2. Council note the project delivery timeline, with construction to commence in late 2026 and completion by mid-2027 (per the TfNSW Safer Roads Program grant agreement).

The LATM Plan has been updated in response to the submissions and incorporating TfNSW comments.

Next steps for the LATM project

Next steps in the process include:

  • Detailed Design: finalising the detailed design incorporating the feedback and taking into consideration site constraints (April to June 2026).
  • Procurement of construction contractor (July-Aug 2026).
  • Construction: commencing late 2026 and completed by 30 June 2027 to meet grant requirements.


Progress Update - 25 February 2026

At its meeting on 28 July 2025, Council resolved that:

1.1 The Boronia LATM Option C be adopted by Council.
1. 2. Detail designs be undertaken and community consultation be carried out prior to construction.

The community were able to view and have their say on the final concept design for the proposed traffic calming measures in this document. The concept design incorporates minor changes to better suit the Boronia Precinct road network environment and to address the feedback initially received by the community.

Works are expected to begin in late 2026.

A Community information session was held on Monday 9 March to give residents the chance to view the final concept design in person.

Background

Council has been successful in receiving State Government funding to create a 40km/h local area traffic zone in the Boronia precinct.

The Safer Roads Program grant from Transport for NSW will be used to implement a local area traffic management (LATM) plan that will improve traffic and road safety in the Boronia precinct.

Traffic calming devices will be installed in local streets inside the boundary of Pittwater, Ryde and Park Road and High Street as displayed below and within the Boronia Precinct Local Area Traffic Management Plan. The speed will be reduced to 40km/h on these streets.

The identified streets in the Boronia precinct are often used by motorists who are looking to avoid the main road network, but are not local road users (rat running). This causes extra stress on these identified local streets in Boronia, decreasing local amenity and increasing safety concerns.

The project aims to change driver behaviour by installing physical speed barriers such as speed humps and raised pedestrian crossings, and reinforcing that this is a local street precinct where lower safer speeds are appropriate.

Low speed zones lead to broader benefits in creating an environment that supports pedestrian activity and urban amenity.

At its Meeting on 24 February 2025, Council resolved to endorse the proposed traffic calming devices mentioned above within the Boronia Precinct Local Area Traffic Management Plan, and to place the proposal on public exhibition for a period of 28 days.

Community feedback was undertaken from Thursday 3 April to 5pm Sunday 4 May 2025.

A community meeting was also held at the Boronia Park Sports and Community Facility on Tuesday 29 April 2025.

All feedback will be collated and will be used to inform the detailed design.

Council is committed to ensuring the community has their say on any proposed changes to traffic conditions on local streets.

The projected must be completed by mid-2027 as per the grant agreement with Transport for NSW.

  • CLOSED: This survey has concluded.

    Please provide your feedback on the Boronia Precinct Local Area Traffic Management Plan final concept designs by completing this form.

    Share Have your say: Boronia Precinct Local Area Traffic Management Plan final designs on Facebook Share Have your say: Boronia Precinct Local Area Traffic Management Plan final designs on X (formerly Twitter) Share Have your say: Boronia Precinct Local Area Traffic Management Plan final designs on Linkedin Email Have your say: Boronia Precinct Local Area Traffic Management Plan final designs link
Page last updated: 22 Jun 2026, 05:48 PM